8/25/21: First team meeting with Mike Sabo. He explained what he wanted, showed an example, and left us room for any questions.
9/10/21: Talked with Mike to understand more about our audience and problem. He directed us to the specific aims section of a grant.
9/11/21: Team meeting to clear any questions about the project and made sure we were all on the same page. Started to develop a plan for the semester and a designated meeting time. Then completed the Project Scope.
9/13/21: Morning meeting with Dr. Klaesner to go over our Project Scope, his biggest concern were our specs.
9/13/21: Met with team in the evening to revise and edit Project Scope and make necessary changes after the morning meeting.