Week 23 Report (3/11)

We met on Wednesday to organize the lab notebook and plan the tasks to complete for the rest of the semester.  We plan to finish the prototype device by the first week of April. 

On Thursday, we met with Ziang to update him on our progress. He mentioned that he expects IACUC approval within the next week or so for the device. We also started coordinating with him to set up the verification and validation testing that we hope to start in mid-April.